September 8, 2022 at 3:13pm

Project Completed

Northbrook Park District is replacing the basketball court at Indian Ridge Park. Soil borings, engineering work and construction is scheduled to take place in the fall of 2022. Landscape and bench improvements will also be made when the court is replaced. This project is in conjunction with a resident donation.

Project Updates
October 28, 2022
Concrete will be poured on Tuesday, November 8 (weather permitting). Asphalt is scheduled by the end of November. Color coating and final grading will be completed in the Spring of 2023.

September 14, 2022
Contractor is scheduled to begin work on the basketball court on Monday, September 19 (weather permitting).