
September 8, 2022 at 3:13pm
Project Completed
Northbrook Park District is replacing the basketball court at Indian Ridge Park. Soil borings, engineering work and construction is scheduled to take place in the fall of 2022. Landscape and bench improvements will also be made when the court is replaced. This project is in conjunction with a resident donation.
September 14, 2022 For more information about the Indian Ridge Park Basketball Court Replacement, contact us by email or call 847-291-2960.
Concrete will be poured on Tuesday, November 8 (weather permitting). Asphalt is scheduled by the end of November. Color coating and final grading will be completed in the Spring of 2023.
Contractor is scheduled to begin work on the basketball court on Monday, September 19 (weather permitting).